Summary

The Blackwater HVDC station connects the two asynchronously operated ac systems of Public Service Company of New Mexico (PNM) and Southwestern Public Service (SPS). It allows for bidirectional power transfer between the Western and the Midwestern power grids of the USA.


The nominal power is 200 MW, continuous overload is 220 MW at maximum ambient condi­tions using redundant equipment. Main reason for the installation of the Blackwater station was to minimize costs for electrical energy generation.


A remarkable feature is the station's reac­tive power capability. The station controls, besides the active power, ac voltage and adjusts itself to the optimum operating point.

The station was designed, built, commissioned and released for commercial operation within less than two years work lasting from Feb. 83 to Dec. 31, 84.

Additional informations

Publication type Session Materials
Reference 14-04_1986
Publication year
Publisher CIGRE
Study committees
  • DC systems and power electronics (B4)
File size 445 KB
Price for non member 30 €
Price for member Free

Authors

BORG, HJORTSBERG, HOGLUND, HORNFELDT, DOHERTY, ENGLER

Keywords

back-to-back tie, long AC line, AC voltage control, loss minimization

Design and commissioning of the Blackwater back-to-back station (USA
Design and commissioning of the Blackwater back-to-back station (USA