This WG examined power system architecture design without any constraints except four, generation distribution, demand distribution, land condition, and acceptable reliability. For a fictitious region for the green field network designing ten designs were received. The finding is that the knowledge planners' use is classified into two types; tacit knowledge and explicit ones. They need to understand that they utilize both types of knowledge to design uncertain network.

Additional informations

Publication type Electra
Reference ELT_274_5
Publication year 2014
Publisher CIGRE
Study committees Power system development and economics (C1)
Working groups WG C1.19