Summary
Series compensation increases the transfer capacity for long transmission lines. Overcompensation (compensation degree above 100 %) is sometimes an option in grid expansion. No significant technical issues preventing overcompensating were found but overcompensation leads to a more complex power system and requires analyses on steady state and transient voltages, transient recovery voltages, resonances and protection aspects, described in the technical brochure.
Additional informations
| Publication type | Technical Brochures |
|---|---|
| Reference | 829 |
| Publication year | |
| Publisher | CIGRE |
| Study committees |
|
| Working groups | JWG C4/B5.41 |
| File size | 11 MB |
| Pages number | 154 |
| Price for non member | 280 € |
| Price for member | Free |